50–250 MW
Unusual Outage
Cable Management System
Frequent Cable Untwist Stops Identified
"Kavaken identified unusually frequent cable untwist stops in one turbine compared to others on the same site."

The Impact
5 MWh production increase
The Issue
Frequent 'Stop for Cable Untwist' alarms were observed on one turbine, causing repeated short outages.
The Action
Kavaken’s analysis revealed that this turbine had far more untwist stoppages than others on the site over the past year. The insight was shared with the operations team, leading to planned inspection and corrective maintenance on the cable management system to prevent further production losses.